- The sole, hatch, deck, and side cubbies have been installed, glassed, faired and sanded.
- The skeg has been installed and the underside has been faired and sanded. For the skeg I used some hard maple I had lying about the shop; it's also been glassed.
- The fairing process took much longer than expected. I used my drywall taping knifes and feathering knife to do most of the work. Both the upper and underside took two coating of fairing compound with sanding between coats.
- I've sent the templates to Marine Mat for quote.
- The upper side has been curing for about a week, so it'll be ready for primer and paint this week. The underside will be sanded back tomorrow and ready for primer and paint next week after Christmas.
- I am using S3 Pennant (yacht) primer with the EMC Quantum 99 top coat for the sides and deck. I will be applying a graphite/epoxy coating to the below waterline section.
- Once the paint is on, the lights and hardware will be installed. I've got Tessilmare R30 rub rail cut, and all holes epoxied and drilled.